Policy

  1. The Cooperative will permit the interconnection and parallel operation of Qualifying Facilities, consistent with Cooperative Policy 602 and Cooperative rules and regulations.
  2. With respect to DR facilities that are not Qualifying Facilities, the Cooperative will permit the interconnection and parallel operation of Permitted Synchronized Generation Facilities where (1) Buckeye has approved the same, (2) such facilities meet all of the Cooperative’s Rules and Regulations, and (3) such facilities are equal to or greater than 25 kW but not more than 10 MVA.
  3. DR facilities are otherwise not permitted to interconnect with and operate in parallel with the Cooperative’s electric distribution facilities except as approved by the Cooperative’s Board of Trustees on a case by case basis.